Bonneville Power Administration

http://www.bpa.gov

Link to BPA Home Page Skip Primary Navigation
EFW Home Page
BPA Home Triangle Bullet Point EFW Home Triangle Bullet Point Information for Contractors Triangle Bullet Point Contract Changes
This is a spacer graphic
This is a spacer graphicTriangle bullet pointUsing Pisces

This is a spacer graphicTriangle bullet pointStatements of Work/Work Elements

This is a spacer graphicTriangle bullet pointProject and Contract Budgets

This is a spacer graphicTriangle bullet pointReporting Requirements

This is a spacer graphicTriangle bullet pointContract Checklist

This is a spacer graphicTriangle bullet pointContract Changes

This is a spacer graphicTriangle bullet pointReport Center


Adjust your View!
Link to Firstgov


Contract Changes



BPA recognizes that project needs and conditions may change throughout the year, and that project proponents may need to request changes to their scope, budget or timeline to adapt. The procedures for requesting such changes are described below.

  • NOTE: Contractors may not implement changes to scope, budget or performance period prior to receipt of a signed contract amendment or written authorization from the BPA Contracting Officer.

  • Scope Changes
    BPA project managers and contractors are responsible for ensuring that the work they carry out aligns with the intent of the Council and BPA as described during project selection. Most changes in scope must be approved by the Council and BPA; minor changes may be made by the BPA Contracting Officer (CO). Any contractors considering a contract scope change should notify their BPA project manager as soon as possible.

  • Budget Changes
    • Budget-neutral changes -- such as budgetary line item transfers -- that do not result in a change to the contract value may be made by BPA and the contractor and do not require Council or CBFWA approval. For transfers greater than 5% of the total contract budget, contractors must send a written request to the BPA Contracting Officer. Budgetary line item transfers totaling less than 5% of the total contract budget are within the discretion of the contractor, and do not require BPA approval or action. See Bonneville Purchasing Instructions (BPI), Part 25, Clause 25-4).
    • Budget increases: increases of any amount, or rescheduling of work and associated funding from one fiscal year to the next, must be approved by BPA, the Council, and CBFWA via the Budget Oversight Group (BOG), which typically reviews requests quarterly. Forms and instructions for requesting such changes are available on CBFWA's website at: http://www.cbfwa.org/mods/intro.cfm


  • Schedule Changes
    BPA may allow a No Cost Time Extension (NCTE) of a contract performance period. As the name implies, NCTEs permit additional time to complete contract work, not additional funding. NCTEs are intended for contracts that will not be renewed. Requests for NCTEs should be made to the BPA Contracting Officer (CO) via the Contracting Officer's Technical Representative (COTR).

  • Other Changes
    Changes to contract terms such as payment schedule (Net 15, Net 30, etc.) or agreement type usually require a written request to the BPA CO. To identify the CO for a particular contract, search Pisces or contact the COTR.

If you believe information on this site is missing or in error, please Submit that comment here.
NOTICE: This site is owned and operated by the Bonneville Power Administration, United States Department of Energy. Use of this system is monitored by system and Security personnel. Anyone using this system consents to MONITORING of this use by system or security personnel. BPA Privacy Policy

     
 Page last reviewed on 7/15/2008 2:49:01 PM